The Pacifica Construction Progress Update

Construction of The Pacifica continues to progress on programme!
Progress Status – February 2020:

  • Top of the jump form reaches L54 with slab poured to L50
  • Façade installation up to L44 and continues to chase the super structure
  • Internal fit out well advanced throughout the tower
  • Superstructure top out April/May with crane removal to follow
  • On target for completion Q4 2020
  • Latest construction time-lapse video now available to view on The Pacifica website and Facebook Page
  • Our next purchaser event is scheduled for 17 March 2020 – invite to be out to Purchasers end of February