20 February 2020

2020 Summer Construction Progress Update

Construction of The Pacifica continues to progress on programme!
Progress Status – February 2020:
• Top of the jump form reaches L54 with slab poured to L50
• Façade installation up to L44 and continues to chase the super structure
• Internal fit out well advanced throughout the tower
• Superstructure top out April/May with crane removal to follow
• On target for completion Q4 2020
• Latest construction time-lapse video now available to view on The Pacifica
website and Facebook Page
• Our next purchaser event is scheduled for 17 March 2020 – invite to be
out to Purchasers end of February