Light House – Progress Update

We are pleased to report that construction progressed well in April on Lighthouse Tower with the following updates:

  • Concrete pour of levels to Level 17 as of 13/05
  • Core walls have reached level 19
  • Glass and metal façade has reached level 13
  • Form work has been stripped in key areas including amenities and pool located on level 8
  • Level 3, 4 & 5 installation of joinery and final finishes