MENU
close

23 August 2016

Light House – Progress Update

Construction on Light House Tower is progressing smoothly with the following updates as of 23 August 2016:

  • Structural core has been completed to Level 39.
  • Concrete pours of levels to Level 37.
  • Glass and metal façade to Level 32 has been completed.
  • Joinery installed to Level 19.
  • Defecting to Level 5.