Construction on Light House has made rapid progress this past month with the following updates as of 22 September 2016:
- Structural core has been completed to Level 46.
- Concrete pours of levels o 43.
- Glass and metal façade to Level 37 has been completed.
- Joinery installed to level 26.
- Defecting completed to Level 14.