-The final ‘roof’ concrete slab has been poured and there are no more concrete works

-Concrete pump (red pipes lying in lift lobbies) are being removed

-Façade glass (to the very top) due for final installation early October

-Sky Residences and lounge complete forecast for Early November

-Tower Cranes coming down late November 2019

-Mezzanine Plaza opening early December 2019

-Retail ‘base building’ complete late January 2020

-Multiplex ‘complete’ February 2020

-Retailers beginning fit outs from January through to June 2020 depending on size

-Retail tenants forecast – Asian grocer/supermarket, destination restaurant to plaza, lifestyle/coffee