20 August 2019
Swanston Central Progress Update
- The final ‘roof’ concrete slab has been poured and there are no more concrete works
- Concrete pump (red pipes lying in lift lobbies) are being removed
- Façade glass (to the very top) due for final installation early October
- Sky Residences and lounge complete forecast for Early November
- Tower Cranes coming down late November 2019
- Mezzanine Plaza opening early December 2019
- Retail ‘base building’ complete late January 2020
- Multiplex ‘complete’ February 2020
- Retailers beginning fit outs from January through to June 2020 depending on size
- Retail tenants forecast – Asian grocer/supermarket, destination restaurant to plaza, lifestyle/coffee