Construction of Light House Tower is progressing at a rapid speed with the following updates as of 8th June 2016:
- Structural core has been completed to Level 25
- Concrete pours of levels to Level 22
- Glass and metal façade to Level 19 has been completed.
- Joinery installed to level 10
- Amenities level (pool/gym/other) beginning final finishes