With construction commenced in August 2016, Swanston Central, 170 Victoria Street is currently advancing at a healthy pace with the following updates as of 20 April 2017:
- Bulk excavation, site retention, raft slab, stormwater and main services infrastructure lead in complete
- Lower ground/basement, ground core/concrete work complete
- 2 cranes on site to be ready for the main ground, first and podium structure/slabs to be formed.