Construction of Swanston Central has been progressing at a rapid speed. Anticipated settlement time for stage one (up to and including level 21) is in September 2018.
Works completed to the end of April 2018:
- Floor levels have been poured to L26
- Main entrance lobby feature ceiling being installed, as well as marble to columns
- Tiling to L6 pool area, and spas well underway
- Apartments being fitted with joinery to level 15, tiling and painting