Construction on Swanston Central continues to progress on program with the following updates in December 2017:
Podium structural completion
- Lift and central core has reached level 19
- Large feature columns that surround the podium have been completed and beginning to receive final finishes and feature cladding
- “Podium” levels which are ground to Level 6 are complete
- External glass building fabric has begun to be installed from Level 7, which will follow the floor cycles
- Final finishes to main entrance lobby and L6 amenities have been selected and are being sourced from different parts of the world