Swanston Central Progress Update

Construction on Swanston Central continues to progress on program with the following updates in December 2019:

  • Building structure 100% completed.
  • Building façade 100% completed
  • Both the tower cranes have been removed.
  • L47 residents amenity level opened
  • Retail bluestone building works to be completed in early 2020