Construction of Swanston Central is progressing well and the first stage of settlements will occur in the third quarter of this year. Construction Update to end May:
- Floor slabs have reached Level 30
- Lift core remain slightly ahead at Level 35
- Level 6 amenities are well underway with tiling completed to the pool and the Cabana areas being fitted out
- Main entrance lobby feature ‘fish scale’ ceiling almost complete, feature lighting installation and marble cladding complete
- Prototype apartments are being furnished for furniture display by Two Style for online purchase