25 November 2016

Light House Progress Update

Construction on Light House continues to progress on program with the following updates as of 25 November 2016:

  • Structural core has been completed to Level 58.
  • Concrete pours to Level 56.
  • Glass and metal façade to Level 52 has been completed.
  • Joinery installed to Level 40.
  • Defecting completed to Level 27.

23 August 2016

Light House – Progress Update

Construction on Light House Tower is progressing smoothly with the following updates as of 23 August 2016:

  • Structural core has been completed to Level 39.
  • Concrete pours of levels to Level 37.
  • Glass and metal façade to Level 32 has been completed.
  • Joinery installed to Level 19.
  • Defecting to Level 5.

26 July 2016

Light House – Progress Update

Construction on Light House Tower is progressing steadily with the following updates as of 26 July 2016:

  • Structural core has been completed to Level 31.
  • Concrete pours of levels to Level 29.
  • Glass and metal façade to Level 24 has been completed.
  • Joinery installed to level 13.
  • Amenities level (pool/gym/other) structural areas completed. Cosmetic fitout due to begin in August.

30 March 2016

Light House – Progress Update

With construction commencing in February 2015, Lighthouse Tower, 450 Elizabeth Street is currently advancing at a healthy pace with Level 11 poured and facades up to Level 6 now completed. Core is finished to Level 14.

  • Level 9 pool slab poured
  • Façade complete to Level 6
  • Core complete to Level 14
  • Finishes Level 2 – Level 5 (in progress)