23 August 2016

Light House – Progress Update

Construction on Light House Tower is progressing smoothly with the following updates as of 23 August 2016:

  • Structural core has been completed to Level 39.
  • Concrete pours of levels to Level 37.
  • Glass and metal façade to Level 32 has been completed.
  • Joinery installed to Level 19.
  • Defecting to Level 5.

26 July 2016

Light House – Progress Update

Construction on Light House Tower is progressing steadily with the following updates as of 26 July 2016:

  • Structural core has been completed to Level 31.
  • Concrete pours of levels to Level 29.
  • Glass and metal façade to Level 24 has been completed.
  • Joinery installed to level 13.
  • Amenities level (pool/gym/other) structural areas completed. Cosmetic fitout due to begin in August.

29 April 2016

Light House – Progress Update

We are pleased to report that construction progressed well in April on Lighthouse Tower with the following updates:

  • Concrete pour of levels to Level 17 as of 13/05
  • Core walls have reached level 19
  • Glass and metal façade has reached level 13
  • Form work has been stripped in key areas including amenities and pool located on level 8
  • Level 3, 4 & 5 installation of joinery and final finishes