25 November 2016

Light House Progress Update

Construction on Light House continues to progress on program with the following updates as of 25 November 2016:

  • Structural core has been completed to Level 58.
  • Concrete pours to Level 56.
  • Glass and metal façade to Level 52 has been completed.
  • Joinery installed to Level 40.
  • Defecting completed to Level 27.

24 October 2016

Light House – Progress Update

Construction on Light House has made rapid progress this past month with the following updates as of 24 October 2016:

  • Structural core has been completed to Level 52.
  • Concrete pours to Level 50 .
  • Glass and metal façade to Level 45 has been completed.
  • Joinery installed to Level 35.
  • Defecting completed to Level 20.

22 September 2016

Light House – Progress Update

Construction on Light House has made rapid progress this past month with the following updates as of 22 September 2016:

  • Structural core has been completed to Level 46.
  • Concrete pours of levels o 43.
  • Glass and metal façade to Level 37 has been completed.
  • Joinery installed to level 26.
  • Defecting completed to Level 14.

29 April 2016

Light House – Progress Update

We are pleased to report that construction progressed well in April on Lighthouse Tower with the following updates:

  • Concrete pour of levels to Level 17 as of 13/05
  • Core walls have reached level 19
  • Glass and metal façade has reached level 13
  • Form work has been stripped in key areas including amenities and pool located on level 8
  • Level 3, 4 & 5 installation of joinery and final finishes