25 November 2016

Light House Progress Update

Construction on Light House continues to progress on program with the following updates as of 25 November 2016:

  • Structural core has been completed to Level 58.
  • Concrete pours to Level 56.
  • Glass and metal façade to Level 52 has been completed.
  • Joinery installed to Level 40.
  • Defecting completed to Level 27.