Construction on Light House has made rapid progress this past month with the following updates as of 24 October 2016:
- Structural core has been completed to Level 52.
- Concrete pours to Level 50 .
- Glass and metal façade to Level 45 has been completed.
- Joinery installed to Level 35.
- Defecting completed to Level 20.