Construction on Light House Tower is progressing steadily with the following updates as of 26 July 2016:
- Structural core has been completed to Level 31.
- Concrete pours of levels to Level 29.
- Glass and metal façade to Level 24 has been completed.
- Joinery installed to level 13.
- Amenities level (pool/gym/other) structural areas completed. Cosmetic fitout due to begin in August.