25 November 2016

Light House Progress Update

Construction on Light House continues to progress on program with the following updates as of 25 November 2016:

  • Structural core has been completed to Level 58.
  • Concrete pours to Level 56.
  • Glass and metal façade to Level 52 has been completed.
  • Joinery installed to Level 40.
  • Defecting completed to Level 27.

24 October 2016

Light House – Progress Update

Construction on Light House has made rapid progress this past month with the following updates as of 24 October 2016:

  • Structural core has been completed to Level 52.
  • Concrete pours to Level 50 .
  • Glass and metal façade to Level 45 has been completed.
  • Joinery installed to Level 35.
  • Defecting completed to Level 20.

22 September 2016

Light House – Progress Update

Construction on Light House has made rapid progress this past month with the following updates as of 22 September 2016:

  • Structural core has been completed to Level 46.
  • Concrete pours of levels o 43.
  • Glass and metal façade to Level 37 has been completed.
  • Joinery installed to level 26.
  • Defecting completed to Level 14.

23 August 2016

Light House – Progress Update

Construction on Light House Tower is progressing smoothly with the following updates as of 23 August 2016:

  • Structural core has been completed to Level 39.
  • Concrete pours of levels to Level 37.
  • Glass and metal façade to Level 32 has been completed.
  • Joinery installed to Level 19.
  • Defecting to Level 5.

26 July 2016

Light House – Progress Update

Construction on Light House Tower is progressing steadily with the following updates as of 26 July 2016:

  • Structural core has been completed to Level 31.
  • Concrete pours of levels to Level 29.
  • Glass and metal façade to Level 24 has been completed.
  • Joinery installed to level 13.
  • Amenities level (pool/gym/other) structural areas completed. Cosmetic fitout due to begin in August.